KPIInformation Technology

Sprint Velocity

Average number of story points completed per sprint over a rolling period

What is Sprint Velocity?

Sprint velocity is the average amount of work, measured in story points, that a team completes in a sprint. It shows the pace at which a team delivers.

Teams use it to plan how much work to take on, but it is a planning tool for a single team, not a measure of productivity to compare between teams.

How this KPI is measured

Function
Information Technology
Sub-function
Software Delivery
Industry
All Industries
Type
Lagging
Impact
Efficiency
Unit
pts
Measurement frequency
Per sprint
Formula
Sum of story points completed in last N sprints / N

How to calculate it

Add up the story points completed in the last several sprints and divide by the number of sprints.

For example, if a team completed 32, 28, 35 and 33 points over four sprints, velocity is (32 + 28 + 35 + 33) / 4 = 32 points.

Story points are relative estimates that differ between teams, so velocity should only be compared for the same team over time.

Where it is used

  • Planning sprints

    Choose realistic amounts of work.

  • Forecasting delivery

    Estimate when work will finish.

  • Spotting change

    See when capacity shifts.

How to improve it

Tips and common mistakes

  • Never compare velocity between teams.
  • Pressure to raise velocity leads to inflated estimates.
  • Focus on delivered value, not points.